Infrastructure Development Projects
Installation of Highmast Light
No. of Projects | :- | 51 | |
Total Amount | :- | 11.39 Crore | |
No. of Projects completed | :- | 25 | |
No of Ongoing Projects | :- | 26 |
Sl No | Project | Outlay (Rs. in lakh) |
Status |
---|---|---|---|
1 | High mast light installation at Pallithura | 32 | Work Completed |
2 | High mast Light, Valiyathura | 13.58061 | Work Completed |
3 | Installaltion of highmast light in Poonthura | 24 | Work Completed |
4 | Installation of High mast light at Kannamthura | 40 | Work Completed |
5 | Installation of high mast light at Mampally | 32 | Work Completed |
6 | Installation of High mast light at Valia veli | 17 | Work Completed |
7 | Installation of high mast light in Puthukurichi | 9.5 | Work Completed |
8 | Installation of High mast lights at Thiruvananthapuram (10 Nos) | 70 | Work Completed |
9 | Installation of highmast light in Vizhinjam | 52 | Work Completed |
10 | Installation of non soalr high mast light in Paruthiyoor | 24 | Work Completed |
11 | Installation of solar street lighting at Pallithura | 20.5 | Pre-project activities in progress |
Sl No | Project | Outlay (Rs. in lakh) |
Status |
---|---|---|---|
1 | High mast light installation at Alappad | 16 | Work Completed |
2 | Installation of High mast lights at Kollam (2Nos) | 14 | Work Completed |
3 | Installation of non solar high mast light in Thankassery | 24 | Work Completed |
4 | Installation of Solar High mast light at Eravipuram | 20 | Work Completed |
5 | High mast light installation at Thekkumbhagom and Thevalakkara | 16 | Work in Progress |
Sl No | Project | Outlay (Rs. in lakh) |
Status |
---|---|---|---|
1 | Installation of non solar high mast light in Pallithode | 14 | Work Completed |
2 | Installation of solar high mast light in Arthungal | 14 | Work Completed |
3 | Installation of solar high mast light in Kattoor | 14 | Work Completed |
4 | Installation of High mast lights at Alappuzha (3 Nos) | 21 | Work in Progress |
5 | Installation of non solar high mast light in Arthungal | 7 | Work yet to Commence |
6 | Installation of non solar high mast light in Kattoor | 7 | Work yet to Commence |
7 | Mounting of high mast lights 3Nos.@ 8lakh and Rural Electrification at Karuvatta | 42.8 | Pre-project activities in progress |
Sl No | Project | Outlay (Rs. in lakh) |
Status |
---|---|---|---|
1 | Highmast light installation at Vaikom | 16 | Pre-project activities in progress |
Sl No | Project | Outlay (Rs. in lakh) |
Status |
---|---|---|---|
1 | Installation of non solar high mast light in Udayamperror | 21 | Work Completed |
2 | Installation of solar high mast light in Kumbalam | 21 | Work Completed |
3 | Installation of non solar high mast light in Pallippuram | 14 | Work yet to Commence |
4 | Mounting of high mast lights 3Nos.@ 8lakh at Poothotta | 24 | Pre-project activities in progress |
5 | Mounting of high mast lights 3Nos.@ 8lakh at udeyamperoor | 24 | Pre-project activities in progress |
Sl No | Project | Outlay (Rs. in lakh) |
Status |
---|---|---|---|
1 | High mast Light, Anapuzha | 8 | Work Completed |
2 | Electrification at vadanapally | 29.91 | Work in Progress |
3 | Installation of High mast lights at Thrissur (1 Nos) | 7 | Work in Progress |
4 | High mast light installation at Vadanapally | 24 | Pre-project activities in progress |
5 | Installation of Solar High mast light at Blangad | 20 | Pre-project activities in progress |
6 | Mounting of high mast lights 3Nos.@ 8lakh at mala | 24 | Pre-project activities in progress |
Sl No | Project | Outlay (Rs. in lakh) |
Status |
---|---|---|---|
1 | Installation of solar high mast light in Paravanna | 14 | Work Completed |
2 | Installation of high mast light in Paravanna | 21 | Work yet to Commence |
3 | Installation of non solar high mast light in Ariyalloor | 28 | Work yet to Commence |
4 | High mast light installation at Koottayi | 16 | Pre-project activities in progress |
Sl No | Project | Outlay (Rs. in lakh) |
Status |
---|---|---|---|
1 | High mast light, Beypore and Marad | 14.1 | Work Completed |
2 | Installation of High mast lights at Kozhikkode (3 Nos) | 21 | Work Completed |
3 | Installation of non solar high mast light in Elathur | 14 | Work yet to Commence |
4 | Installation of non solar high mast light in Koilandy | 24 | Work yet to Commence |
5 | High mast light installation at Madapally | 32 | Pre-project activities in progress |
6 | Installation of High mast light at Vellayil | 20 | Pre-project activities in progress |
Sl No | Project | Outlay (Rs. in lakh) |
Status |
---|---|---|---|
1 | Installation of High mast lights at Kannur(1 Nos) | 7 | Work Completed |
2 | Installation of non solar high mast light in Chalil Gopalpetta | 35 | Work Completed |
Sl No | Project | Outlay (Rs. in lakh) |
Status |
---|---|---|---|
1 | Installation of high mast light in Kottikulam | 14 | Work yet to Commence |
2 | Installation of highmast light in Bengara Manjeswaram | 14 | Work yet to Commence |
3 | High mast light installation at Kasaba | 56 | Pre-project activities in progress |
4 | High mast light installation at Koippadi | 32 | Pre-project activities in progress |